FMG - Team 45

Port Hedland

Greenfields Port Facilities Project

Client/EPCM
Team 45 / Worley Parsons

Value
$24.6 Million

Description
The Construction of the initial Port Handling facilities and the expansion of the Optimisation Stage of the Point Anderson works was completed over 26 months. Comprising 12,890 cubic meters of structural concrete which comprised from Transfer Stations, Ends Stops for Reclaimers and Stackers, Electrical Substations, Retaining Walls, Remediation and detail concrete installation on the Car Dumper and miscellaneous Concrete structures throughout the Port works.


FormAction enjoyed a mutual respected relationship, offering flexibility and safety behaviours that kept us onsite for the duration of the works until completion.